Pars Petrochemical Port

Installation & commissioning of the DCS control system for Pars Petrochemical Port and establishment of MODBUS communication with other complexes.
Client: Terminals and Tanks Petrochemical Co.
Status: Final Handover




In addition to the installation & commissioning of DCS, ESD & F&G equipment for the eastern and western jetties & meterings, communication signals between petrochemical complexes (Mobin, Pars, Arya Sasol, Jam, Pardis, Zagros & Noori) and eastern and western parts were established using the MODBUS protocol.


Razi Petrochemical Co

Replacement & renovation of the control system and instrumentation of the soil crain for the shipping unit of Razi Petrochemical Co. Replacement of the existing DC motors & drives with AC equivalents.
Client: Razi Petrochemical Co.
Status: Ongoing


Oil storage tanks for 11 cities

Supply & construction of control panels for the oil storage tanks of 11 cities. (Khoy, Khalkhal, Iranshahr, Hamedan, Zahedan, Ghom, Sabzevar, Tabriz, Zanjan, ...)
Client: Khatam al-Anbia base, Shahid Rajaee Org.
Status: Final Handover

Tehran Refinery Bitumen Unit

Supply, construction, programming & commissioning of the control system for the bitumen export terminal.
Client: Pasargad Oil Co.
Status: Final Handover

Bandar Abbas Bitumen Export

Design, supply, construction, programming, and commissioning of the control system for Bandar-Abbas bitumen export terminal.
Client: Pasargad Oil Co.
Status: Final Handover

Salman Offshore Platform

Programming and commissioning of the dehydration packages for KPP and GLP platforms belonging to Salman oil & gas offshore field.
Client: Petroiran Development Co.
Status: Final Handover

Fanavaran Petrochemical Co

Design, supply, programming, and commissioning of the control systems for the MV substation and the CO unit located in site No.3 of the petrochemical special economic zone.
Client: Fanavaran Petrochemical Co.
Status: Final Handover

Marun Petrochemical Co

Marun Petrochemical Co.

Kermanshah Polymer Co

Supply of the DCS/PLC systems for the utility and offsite units of Kermanshah polymer co.
Status: Final Handover

Supply, installation, & commissioning of the control system, and installation & commissioning of the electrical equipment for the offsite Felman water wells of Kermanshah polymer refinery.
Status: Final Handover

Establishment of an integrated control system by transferring the control systems of the offsite units (Nitrogen, Hydrogen, steam, etc) all to the central control room. Replacement of the control panel of the Nitrogen unit and re-commissioning of this unit. Debugging of the Steam unit control program.
Status: Warranty Period

Palibaba & Bardaspi P.Stations

Design, supply, construction, programming, and expansion of the existing control systems for Palibaba and Bardaspi pumpstations, located in Lorestan Province.
Client: Pars Kayhan Co.
Status: Final Handover

Bandar Imam Petrochemical Co

Bandar Imam Petrochemical Co.

Amir Kabir Petrochemical Co

Amir Kabir Petrochemical Co.

Sarkan Pumpstation

Design, supply, construction, and programming of the control system for Sarkan crude oil pumpstation.
Client: Simin Taban Lorestan.
Status: Final Handover

Rey Oil Depot

Installation of the electrical equipment.
Client: Khatam al-Anbia base, Ghorb Nooh.
Status: Final Handover

Abadan Refinery Bitumen Unit

Upgrade, programming & commissioning of the control system for the bitumen unit waste gas incinerator. Addition of an HMI Panel for the improved control & monitoring of the incinerator, completion & debugging of the control program, execution of the initial warm up profile & establishment of the MODBUS connection to the bitumen production unit DCS.

Client: Pasargad Oil Co.

Status: Final Handover

Tehran Chemie Pharmaceutical Co.

Design, supply, installation & commissioning of the electrical panels for the MCC of Tehran Chemie Pharmaceutical Co, using Schneider Electric parts. Design of the control circuitry, installation of busbar & wiring were performed in the panel manufacturing workshop of Jahed Industrial Group. Panels were transported to be installed at the client site.

Client: Tehran Chemie Pharmaceutical Co.

Status: Final Handover

Sepahan Cement

Design, supply, construction, and commissioning of the control system and MV & LV power panels for the mixing and new packing departments.
Status: Handover
Start date: August 2013

Installation of power, control & instrumentation equipment and commissioning of the 3rd phase of the 3300 tons development plan for Sepahan cement plant. Including the departments of cement mill, cement transfer, cement silos, gypsum & slag transfer, clinker transfer, clinker silo & dry slag.
Status: Final Handover
Start date: September 2008
Duration: 5 months

Consulting services and basic & detailed design of power & control equipment for the transfer of cement from the existing silos to the mixing system, cement & slag mixing system department, equipment for the transfer of slag & cement from the line 3 mill to the existing silos, transfer of cement from the new dual silos to the new packing department, a new packing dep. consisting of two packer machines and manual & automatic bag loading machines, and two palleting machines in the old & new packing deps.
Check & approval of other contractors detailed plans,supervision over construction, installation & commissioning of the above equipment & power equipment for other departments.
Status: Final Handover
Start date: January 2013
Duration: 15 months

Client: Sepahan Cement Co.

Sarcheshmeh copper complex

Upgrade and modification of the control system for the southern single crane of Sarcheshmeh copper refinery.

Engineering, design, procurement, construction, installation and commissioning of the EPC:
1 - Supply and installation of Siemens IP64 rated PLC components. Installed in the acidic environment of the refinery.
2 - Programming and commissioning of the crane control & navigation system under special operating conditions.
3 - Design, supply and implementation of all electrical and instrumentation operations on the crane in accordance with the terms and conditions of the German KRUPP consortium with refinery being operational.
4 - Design, manufacture and installation of the operating cabs in accordance with the terms and conditions of the German KRUPP consortium, considering the refinery operating conditions in the acidic environment.
5 - Registration of errors and review and monitoring of all crane operation from the refinery control room.
6 - Communication between the crane and control room through the eastern outdoor wireless system of the complex.
Status : Final Handover
Start date : October 2011
End date : January 2013


Design, supply, construction & programming of the control system for Sracheshmeh copper complex crusher.
Status : Final Handover
Start date : October 2011
End date : January 2013

Supply and manufacturing of the control system for Molybdenum concentrate dewatering plant. CPU panel, remote IO panels, ACC panel & IPC rack were assembled tested & delivered to the client.
Status: Warranty Period


Client: National Iranian Copper Industries

Zanjan Cement

Commissioning of power & control systems of Zanjan cement plant.
Client: Fars & Khuzestan Cement Co.
Status: Final Handover
Start date: July 2007
Duration: 3 Months

Tejarat Mehriz Cement

Design, supply, programming, installation & commissioning of the control system. Client personnel training for operating & troubleshooting of the PLC and monitoring programs of the different departments of the plant. Consultancy on control panel construction & automation section purchases.
Client: Bohrouk cement co.
Status: Final Handover
Start date: February 2007
Duration: 4 months

Zarrin Rafsanjan Cement

Design, Supply, construction, programming, installation & commissioning of the control system for the entire production line of Zarrin Rafsanjan cement plant.
Status: Final Handover
Start date: August 2007
Duration: 6 months

Installation and loaded & unloaded commissioning of power, control & instrumentation equipment of the entire production line and training of the personnel of Zarrin Rafsanjan cement plant.
Status: Final Handover
Start date: April 2008
Duration: 8 months

Client: Zarrin Rafsanjan cement Co.

Khazar Cement

Commissioning of the kiln department secondary PLCs (main burner & precalciner, grate cooler, shock blaster)
Client: Khazar cement co.
Status: Final Handover
Start date: October 2007
Duration: 3 months

Azar Abadegan Khoy Cement

Supply, commissioning & operator training for the control panel of the material transfer department.
Client: Azar Abadegan Khoy cement co.
Status: Final Handover

Gharb Cement

Commissioning of the control and power systems for the production line of Gharb cement plant.
Client: Gharb cement co.
Status: Final Handover
Start date: September 2007
End date: March 2008

Shomal Cement

Commissioning of the automation & control systems for the capacity improvement departments of the Shomal cement plant.
Client: Shomal cement co.
Status: Final Handover
Start date: January 2008
Duration: 6 months

Delijan Cement

Commissioning of the power, control & instrumentation systems of Delijan cement plant. Operator personnel training.
Client: Behineh sazan sanat pei
Status: Final Handover
Duration: 8 months

Yasuj Cement

Optimization of the automation system of Yasuj Cement plant. Upgrading the CPU and overhauling the control system to Siemens PCS7 system. Network and PLC equipment supply.
Client: Yasuj cement co.
Status: Final Handover
Start date: Agust 2008
Duration: 3 months

Zabol Cement

Holding PLC theory and workshop training courses for the personnel of the power and control departments of Zabol cement company.(In Zahedan University and at the site of Delijan cement plant.)
Client: Behineh sazan engineering co.
Status: Final Handover
Start date: November 2008
Duration: 4 months

Mobarakeh Steel

Equipment pre-building, pre-assembly & assembly, installation and commissioning of the No.2 casting machine for Esfahan Mobarakeh Steel Co. Including the supply of power, instrumentation & automation equipment and building up the main employers required workforce bank.
Client: Esfahan Power Maintenance Co.
Status: Final Handover
Start date: July 2009
Handover: August 2010
Final Handover: September 2011

Shargh Cement

Commissioning of the power, control and instrumentation systems of the 4th line of Shargh cement plant.
Client: Behineh Sazan Engineering Co.
Status: Final handover
Duration: 4 months

Sadr Steel

Programming and commissioning of the production line control system.
Client: Sadr Foolad Co.
Status: Final handover
Duration: 60 days

Gharb Asia (Torbat) Cement

Detailed design of the power, control and automation systems & supervision services. Installation of automation system & training services. Support for 10 years.
Status: Final handover
Start date: January 2010

Supply of the power and automation systems (hardware and software) for one line with 5000 tons per day clinker production capacity. Support after guarantee period for 10 years.
Status: Final handover
Start date: January 2010
Duration: 4 months

Client: Gharb Asia Cement Co. (Torbat Cement)

Bagheran Cement

Engineering, construction, programming, commissioning and supervision over installation of power and control panels for the mixing salon of Bagheran cement plant. Training of the operator personnel.
Status: Final handover
Duration :3 months

Tabas Golshan Cement

Procurement, construction, installation, and commissioning of the power, control, and instrumentation equipment for the cement mill department of Tabas Golshan cement plant.
Client: Tabas Golshan Cement Co.
Status: Ongoing

Khorasan steel

Consulting services and basic and detailed engineering of power, control and instrumentation systems. Programming of control, automation, and instrumentation of Korasan pelletizing project of Korasan Steel Complex. Supervision over procurement, construction, installation and proper operation of systems.
Client: Parsland Mines & Industries Development Company (PAMIDCO)
Status: Ongoing
Start date: June 2011

Saveh Cement

Supply of the control system (PLC/MCC) for the pump house of well No.1 of Saveh white cement plant.
Client: Saveh Cement Co.
Status: Final Handover
Duration: 45 days

Safa Steel

Supply, construction and programming of control system panels.
Client: Safa Foolad Co.
Status: Final handover
Start date: August 2011

Hormozgan Cement

Supply of the control system for cement mill No.4 of Hormozgan cement plant, using Schneider Electric Premium PLCs and parts.
Client: Hormozgan cement Co.
Status: Final handover
Start date: May 2011
Duration: 102 days

Gohar Zamin Iron Ore

Engineering and preparation of all designs and panel & equipment documents. Supply of the software and programming and procurement of the control system parts for the 4 Megaton per year Gohar Zamin Iron Ore Concentrate plant. Supervision over supply, construction and installation of the control system. Commissioning of the control system and training of the operator personnel.
Client: Fakoor Sanat Tehran Co.
Status: Final handover
Start date: September 2012
Duration: 210 days

Lorestan Steel

Maintenance, repair, and troubleshooting of the rolling line of Lorestal Steel complex. In particular by performing the following steps: Inspection of the the existing control system hardware and software, reporting the required modifications of the hardware, supply of all the technical specifications for the hardware parts and equipment required for system maintenance, and implementation of the modifications in the existing control software and programs as requested by the client.
Client: Sadr Steel Co.
Status: Final Handover
Start date: April 2012
Duration: One year

Dehloran Cement

Commissioning of the power, control and instrumentation systems and cement mill department of Dehloran cement plant.
Client: Toos Niroo Technical Co.
Status: Final Handover
Start date: February 2011
Duration: 3 months

Bojnourd Cement

Construction of the I/O panels for the new silos built under the line 1 capacity increase plan.
Client: Bojnourd Cement Co.
Start date: February 2013
Duration: 2 months

Kordestan Cement

Design, supply, programming and commissioning of the control system for line 1 of hydrated lime of Kordestan cement plant, consisting of 4 control panels.
Client: Kordestan Cement Co.
Status: Handover
Start date: November 2013

Neyriz Cement

Execution of the complete civil and construction operations for production line structures and supporting buildings. Installation of the main equipment and mechanical, power, control and instrumentation structures. Commissioning of the machinery and equipment and performing the cold test procedures for the production line of Neyriz (OPC) cement plant by a consortium of Control Gostar Jahed and Faragir Alborz companies.
Client: Neyriz Cement Co.
Status: Ongoing
Start date: April 2014
Duration: 26 months

Choghart Iron Ore

Supply of the complete ABB brand PLC based control system and other required parts for Choghart Iron Ore Concentrate production lines quality improvement project.
Client: Fakoor Sanat Tehran Co.
Status: Final handover
Start date: August 2014

Design & manufacturing the Siemens PLC based control system for the crusher unit. Programming & commissioning of the control & monitoring system.
Client: Fakoor Sanat Tehran Co.
Status: Warranty Period

Chadormalu Mining & Ind.

Jovein Cement

Supply and commissioning of power and control panels for the hot oil boiler of Jovein cement plant.
Status: Final handover
Start date: January 2009
Duration: 14 days

Supply and commissioning of PLC and MCC panels for the fuel depatment.
Status: Final handover
Start date: April 2009
Duration: 30 days

Client: Rastan Sadr Engineers Co.

Zanjan Tekab gold mine

Installation of power and instrumentation equipment.
Client: Manufacturing Erection Inspection Co.
Start date: September 2010

Gol-Gohar Silicon Recycling

Design, supply, assembly, programming & commissioning of the control system using ABB PLC parts.

Omran Arya Cement

Design, assembly and installation of LVD, MCC, FC & PFC panels for the control & production system of the factory. The equipment was sourced from domestic and international suppliers. Busbar forming, installation & wiring and design & construction of the control circuitry, also assembly of all the peripheral parts were done at Jahed Industrial Group panel construction workshop.
Client: Omran Arya Cement Co.
Status: Ongoing


Zargan Power Plant

Supply of the control system parts for the Unit No.1 of Zargan Power Plant (Ahvaz).
Client: Saba Power & Electricity Industries Co.
Status: Final Handover

Qom combined cycle power plant

Qom combined cycle power plant

Farabi and Dehkhoda plants

Trial & commissioning, renovation and correction of the central control & monitoring systems of Farabi and Dehkhoda sugarcane power plants (located in Khuzestan province), operator personnel training, supervision over design and installation.
Client: Sugarcane and Byproducts Development Co.
Status: Final Handover

Mirza and Amirkabir plants

Mirza and Amirkabir plants

Khuzestan Sugarcane Plan P.P.

Tehran Water Treatment Plant

Programming & commissioning of the control system for Tehran water treatment plant.
Status: Final Handover

WTP for Kerman power plant

Programming & commissioning of the control system for the WTP of the Kerman power plant.
Status: Final Handover

Doosti Dam Water Transfer

Complete engineering operations regarding the the controls system for Doosti dam to Mashhad water transfer line pumpstations.
Client: Shimbar Co.
Status: Final Handover

Guilan Water Treatment Plant

Refurbish, renovation, and commissioning of TSX 47-40 and TSX 67-40 PLC series of Guilan water treatment plant.
Client: Guilan Water & Wastewater treatment plant.
State: Final Handover

Arak Water Pumpstations

Design, engineering and supervision services for power, control, and instrumentation for Arak water pumpstations. From procurement and supervision over construction and installation of all the equipment to the trial and commissioning phase.
Client: Shimbar Co.
Status: Final Handover

Gorgan Waste Water Treatment Plant

Programming, commissioning, and supervision over installation of the control system. Designing the technical documents and obtaining the approval of the supervisor for the project of Gorgan wastewater treatment plant.
Client: Shimbar Co.
Status: Final Handover

Hamedan Water treatment Plant

Programming & commissioning of the control system for Hamedan water treatment plant.
Status: Final Handover

Iran Khodro

Upgrade and replacement of the PLC system for the OP840 machine of the cylinder head line of the trimming salon of Iran Khodro Co. from SMC to Siemens S7.
Client: Iran Khodro Co.
Status: Final Handover

Mirza Sugarcane Processing Plant

Upgrade of the DCS control system of the production salon from Siemens Teleperm M to PCS7, involving replacement of the outdated hardware and software, design, programming, installation, test, trail and commissioning of the new control system.
Status: Final Handover

Programming & commissioning of the control system for the Brown Sugar Processing Department of Mirza Sugarcane Plantation Complex using the Siemens NAHMAT software library.
Status: Ongoing

Tuga Overspeed Test Building BMS

Procurement, installation, programming and commissioning of, and providing the operation and repair training of the personnel for the control system and instrumentation of the BMS system for Tuga overspeed test salon.
Client: Gostaresh Sanat Iran Construction Co.
Status: Final Handover

Dehkhoda Sugarcane Processing P.

Complete procedures of Installation, execution, commissioning, test, handover and training of the electrical & control systems, and instrumentation for the sugar conveyors of Dehkhoda sugarcane processing plant. (Stacking, reclaiming, bag conveying, and truck & rail dock conveyors)
Status: Final Handover

Upgrade of the control system software and program of the raw and processed units of Dehkhoda sugarcane plant to PCS7-v7.1 and commissioning of those units.
Status: Final Handover

Client: Jahad Tahghighat Sanat Co.

Taghdis Porcelain

Reverse engineering and hardware and software upgrade of the control system for the dysfunctional Lippert glazing machines from a Siemens S5 PLC series compatible and PC based HMI system to a Siemens S7 and HMI panel based system.
Client: Taghdis Porcelain Co.
Status: Final Handover

Esfahan Machine Manufacturing Co.

Supply, construction, programming, commissioning and training for the control system.
Status: Final Handover

Salman sugarcane Processing P.

Upgrade of the control & monitoring systems, and the existing industrial network. Training of the personnel of Salman sugarcane power plant.
Client: Salman farsi Agro-Industrial co.
Status: Final Hnadover

Asadabad hospital

Supply and construction of 13 electrical panels and one capacitor bank for Asadabad hospital, Birjand.
Client: Golizeh Shargh Construction Co.
Status: Final Handover

Negin Res. & Comm. Complex

Supply of 221 LV panels for Negin Residential & Commercial Complex, Mashhad.
Client: Arain Construction Co.
Status: Final Handover

IRCRTI greenhouse

Supply & construction of electrical, lighting & control panels. Installation & commissioning of all electrical & instrumentation systems. Installation of cable trays & cabling for Iran Sugarcane Center Research & Training Institute greenhouse.
Client: Rased Sanat Toseae Co.
Status: Ongoing