MOBARAKE STEEL

Home Projects Project Details

    • Pre-construction and pre-assembly of equipment, assembly of equipment, installation and commissioning of casting machine No. 2 of Mobarakeh Steel Company of Isfahan, including preparation of electricity, precision instruments and automation, and creation of a force bank required by the main employer.

      (Electrical and Instrumentation Installation Contractor)

      Isfahan Power Repair Company

      Contract duration 18.5 months from the notification of the contract

      Start of contract 5/3/88

      Temporary delivery 5/13/89

      Final delivery 90/6/29