Pre-construction and pre-assembly of equipment, assembly of equipment, installation and commissioning of casting machine No. 2 of Mobarakeh Steel Company of Isfahan, including preparation of electricity, precision instruments and automation, and creation of a force bank required by the main employer.
(Electrical and Instrumentation Installation Contractor)
Isfahan Power Repair Company
Contract duration 18.5 months from the notification of the contract
Start of contract 5/3/88
Temporary delivery 5/13/89
Final delivery 90/6/29
-